Luxury private estate in the heart of the Peninsula

Rosedale is the perfect Mornington Peninsula lifestyle choice for downsizers and young families who want a quality single level home, in touching distance of everything the region is renowned for.

As its own private estate within Rosebud, Rosedale will have its own community within a community feeling, boasting a peaceful and pretty place to call home.

The residences are spacious, full of character and yet very low maintenance. Be surrounded by like minded people with the very best beaches, golf courses, vineyards, restaurants and lifestyle amenity at your fingertips.

View Project Website

Project details

  • Icon
    LOCATION

    1 Bayview Ave, Rosebud

  • Icon
    COMPLETION

    Mid-June 2026

  • Icon
    STATUS

    Construction Complete

  • Icon
    BUILD

    40 Townhouses

Construction Updates

April 2026

• Driveway work completed

• Final touch ups being completed

• Council inspections and titles in progress

• Landscaping work completed

March 2026

• Driveway work in final stages

• Swale drain work now completed

• Display homes now open for inspections

• Landscaping work in progress

February 2026

– Driveway nearing completion

– Final assembly in bathroom and kitchen areas

– Flooring being installed in rear homes

– Landscaping work in progress

January 2026

– Residences 1-10 flooring being installed

– Kitchen units installed in front residences

– Painting underway in rear residences

– Driveway and landscaping work underway

November 2025

– Residences 1-10 exterior work nearing completion

– Kitchen units being installed units 1-5

– Framing work nearing completion

– Roofing work in progress

OCTOBER 2025

– Residences 1-10 concrete slabs completed

– Framing work in progress

– Roofing being installed

– Interior fit out underway in residences 1-5

SEPTEMBER 2025

– Civil works completed

– Concrete slab work in progress

– Electrical & water works in progress

–  Framing work commencing shortly

AUGUST 2025

– Sewer drainage work complete

– Stormwater drainage work in progress

– Waterfall Gully Rd drainage work commencing

– Pre slab work commencing shortly

MAY 2025

-Swale drain work completed

-Retaining walls nearing completion

-Civil works and pre slabs commencing shortly

MARCH 2025

-Swale drain work in progress

-Retaining walls being installed

-Cutting, benching and filling of site underway