April 2026
• Driveway work completed
• Final touch ups being completed
• Council inspections and titles in progress
• Landscaping work completed
March 2026
• Driveway work in final stages
• Swale drain work now completed
• Display homes now open for inspections
• Landscaping work in progress
February 2026
– Driveway nearing completion
– Final assembly in bathroom and kitchen areas
– Flooring being installed in rear homes
– Landscaping work in progress
January 2026
– Residences 1-10 flooring being installed
– Kitchen units installed in front residences
– Painting underway in rear residences
– Driveway and landscaping work underway
November 2025
– Residences 1-10 exterior work nearing completion
– Kitchen units being installed units 1-5
– Framing work nearing completion
– Roofing work in progress
OCTOBER 2025
– Residences 1-10 concrete slabs completed
– Framing work in progress
– Roofing being installed
– Interior fit out underway in residences 1-5
SEPTEMBER 2025
– Civil works completed
– Concrete slab work in progress
– Electrical & water works in progress
–Â Framing work commencing shortly
AUGUST 2025
– Sewer drainage work complete
– Stormwater drainage work in progress
– Waterfall Gully Rd drainage work commencing
– Pre slab work commencing shortly
MAY 2025
-Swale drain work completed
-Retaining walls nearing completion
-Civil works and pre slabs commencing shortly
MARCH 2025
-Swale drain work in progress
-Retaining walls being installed
-Cutting, benching and filling of site underway