Nestled in the heart of the picturesque suburb of Spring Gully, just a stone’s throw away from the vibrant city of Bendigo, lies an exceptional new development – Spring Hill Estate. If you’re ready to embrace the next chapter of your life and downsize without compromising on comfort and quality, this is the place you’ve been waiting for.

Spring Hill Estate is more than a development; it’s an opportunity for you to embark on a new journey filled with comfort, natural beauty, and a sense of community. If you’re ready to downsize without compromise and embrace a lifestyle that celebrates the best of both worlds, Spring Hill Estate in Spring Gully is your destination.

Don’t miss your chance to be a part of this exciting development. Contact us today to learn more about Spring Hill Estate and secure your slice of downsizer’s paradise near Bendigo. Your tranquil, nature-inspired lifestyle awaits!

View Project Website

Project details

  • Icon
    LOCATION

    190 Retreat Road Spring Gully

  • Icon
    COMPLETION

    December 2026

  • Icon
    STATUS

    Under Construction

  • Icon
    BUILD

    40 Townhomes

Construction Updates

August 2026

– Frame works completed

– Roofing work in progress

– Plastering and painting underway

– Exterior cladding work in progress

July 2026

– Concrete slab work completed

– Framing work nearing completion

– Plumbing and electrical fit out in progress

– Roofing work underway

June 2026

– Concrete slab work in progress

– Framing work underway

– Plumbing and electrical fit out in progress

– Roofing work beginning shortly

May 2026

– Retaining walls completed

– Civil works nearing completion

– Slab work commencing shortly

– Frame work to follow

January 2026

– Retaining walls nearing completion

– Civil works in progress

– Pre slab work commencing shortly

– Concrete slab pouring to follow

November 2025

– Cutting and benching work completed

– Sewer work in progress

– Retaining walls being installed

– Concrete slab works to follow after the break

OCTOBER 2025

– Site cleared of existing structures and foliage

– Cutting and benching work underway

– Civil works commencing shortly

– Concrete slab works to follow shortly after

Back to Projects