Construction Updates

APRIL 2025

-Properties in lock up stage

-Exterior and interior painting in progress

-Interior plastering work completed

-Kitchen cabinets and benches being installed

-Timber flooring and carpet being installed

FEBRUARY 2025

-Roofing work completed

-Exterior cladding being installed

-Interior plastering in progress

-Plumbing and electrical services being installed

-Display home work in progress

January 2025

-Concrete foundation work completed

-Framing work completed

-Roofing work in progress

-Plumbing and electrical services being installed

-Plastering work commencing shortly

November 2024

– Civil works completed

– Concrete slab prep and pouring in progress

– Framing work has commenced

SEPTEMBER 2024

– Cutting and benching is completed

– Retaining walls are installed

– Drainage systems completed

– Kerb and footpath updated

JUNE 2024

– Cutting of sections and roadways in progress

– Retaining walls being installed

– Civil works commencing shortly

MAY 2024

– Site cleared of trees and shrubs

– Levelling of site and footings in progress

– Civil work commencing shortly