Marnie Place is much more than a picturesque setting, it is also a complete lifestyle where you and your family can have everything you want at your fingertips. Your new home is conveniently located and you’ll have everything you’ll need right on your doorstep.

Project details

  • Icon
    LOCATION

    19-27 Marnie Road Kennington

  • Icon
    COMPLETION

    August 2025

  • Icon
    STATUS

    Completed

  • Icon
    BUILD

    34 Townhomes

Construction Updates

AUGUST 2025

– Stage one settled and occupied

– Stage two settled and occupied

– Stage three settlements in progress

JULY 2025

– Stage one completed

– Stage two completed and titles issued

– Stage three properties ready for inspection

-Stage three landscaping work nearing completion

-Residents park work completed

JUNE 2025

-Stage one completed

-Stage two driveway pour completed

-Stage two landscaping nearing completion

-Residents park work underway

-Stage three driveway commencing shortly

MAY 2025

-Stage one nearing completion

-First driveway pour complete

-Landscaping work underway

-Residents park work commencing shortly

-Stages two and three work commencing shortly

APRIL 2025

-Properties in lock up stage

-Exterior and interior painting in progress

-Interior plastering work completed

-Kitchen cabinets and benches being installed

-Timber flooring and carpet being installed

FEBRUARY 2025

-Roofing work completed

-Exterior cladding being installed

-Interior plastering in progress

-Plumbing and electrical services being installed

-Display home work in progress

January 2025

-Concrete foundation work completed

-Framing work completed

-Roofing work in progress

-Plumbing and electrical services being installed

-Plastering work commencing shortly

November 2024

– Civil works completed

– Concrete slab prep and pouring in progress

– Framing work has commenced

SEPTEMBER 2024

– Cutting and benching is completed

– Retaining walls are installed

– Drainage systems completed

– Kerb and footpath updated

JUNE 2024

– Cutting of sections and roadways in progress

– Retaining walls being installed

– Civil works commencing shortly

MAY 2024

– Site cleared of trees and shrubs

– Levelling of site and footings in progress

– Civil work commencing shortly

Back to Projects