An offering of unrivalled luxury in a well established community

Nestled on top of the hill between Hampton Park and Lynbrook sites an exciting residential offering of 25 luxury homes.

A private road from a quiet residential backstreet leads through to the development embracing the mature trees on site that have stood there for decades and framing the Dandenong ranges gifting  sweeping views, creating the most beautiful boulevard for its residents.

Spacious 2 & 3 bedroom family homes with quality fixtures/fittings and thoughtful floor plans make up the offering within this boutique community.

Located near to all the sort after amenities including schools, shops, cafes and the M1 its hard to believe how close they are considering the peaceful and scenic location of this private estate.

View Project Website

Project details

  • Icon
    LOCATION

    21 Meduno Drive, Hampton Park

  • Icon
    COMPLETION

    September 2023

  • Icon
    STATUS

    Completed

  • Icon
    BUILD

    25 Townhomes

Construction Updates

March/April 2022 Update

  • Site cleared of vegetation
  • Excavation completed
  • Retaining walls commenced
  • Perimeter fencing underway

May 2022 Update

– civil works underway

– waste and storm water systems installed

– construction of retaining walls

June 2022 Update

– preparation of site or concrete

– waste and storm water systems installed

– all electrical pre slabs done

July / August 2022 Update

– Concrete foundations nearing completion

– Waste and storm water civil works completed

– Framing to commence shortly

September 2022 Update

– concrete foundations completed

– framing work has commenced

– structural steel work being installed

October 2022 Update

– Framing in progress

– Roof trusses and second level being installed

– Exterior brickwork in progress

– Plumbing and gas piping rough in commenced

November/December 2022 Update

– Framing works nearing completion

– Roof trusses and second level being installed

– Exterior cladding and wrapping underway

– Plumbing and gas piping rough in commenced

January 2023 Update

– Framing works nearing completion

– Windows being installed

– Insulation and plasterboard being installed

– Roofing and guttering being installed

-Plumbing and gas piping works in progress

February/March 2023 Update

– Framing works nearing completion

– Windows being installed

– Insulation and plasterboard being installed

– Roofing and guttering being installed

-Plumbing and gas piping works in progress

April 2023 Update

– Driveway paving work in progress

– Rain water drainage systems being installed

– Interior plastering and painting in progress

– Exterior painting underway

May 2023 Update

– Driveway paving work in progress

– Appliances being installed

– Interior plastering and painting in progress

– Landscaping works commencing soon

June 2023 Update

– Driveway paving work complete

– Landscaping work commencing shortly

– Water tanks being installed

– Exterior painting in progress

July 2023 Update

– Property surveying in progress

– Landscaping work underway

– Fencing and storage sheds being installed

– Retaining walls being installed

– NSN network being connected

August 2023 Update

– Fully completed and individually titled

Back to Projects