A local landmark waterfront project with views over the Hastings Foreshore and Westernport Bay.
91 Marine has an unrivalled location, directly opposite the foreshore and nestled against the town centre.
The project consists of 24 well-appointed residences comprising thoughtful floor plans of a generous size, offered to market at an attractive price point.
Choose either stunning views from the living areas & balconies across parkland and the bay, or a spacious low maintenance backyard suitable for children, pets, or simply a tranquil little garden setting of your own to relax in, there’s something for everyone.
Residents will benefit from being walking distance to all amenities including Hastings shopping strip, market, local schools, public transport, the marina, medical clinics, gymnasiums, walking and riding tracks, sporting clubs and much more.
Construction Updates
February 2022 Update
- Site vegetation cleared
- Building envelope site cut and benching underway
March/April 2022 Update
- Site vegetation cleared
- All excavation completed
- Drainage retention system commenced
May 2022 Update
– civil works commenced
– all drainage and stormwater installed
– electrical power supplies installed
June 2022 Update
– ground floor sab and framing complete
– underground plumbing systems completed
– level one subfloor and framing being installed
– structural steel supports in place
July / August 2022 Update
– Level one roof and insulation being installed
– Windows and ranch sliders installed
– Exterior cladding and rendering commenced
– Common area fit out underway
September Update
– Exterior rendering and trims completed
– Exterior painting on the way
– Interior walls completed and plaster commenced
– Ground floor interior paint started
– Kitchen and bathroom cabinets being installed
October Update
– Exterior paint and paneling completer
– Ground floor paint interior complete
– Electrical and plumbing fit off commenced
– Ground floor tiling being installed
November / December 2022 Update
– Driveway and parking area nearing completion
– Exterior fencing and landscaping in progress
– Ground floor units final stages of finishing
– Cabinetry being fitted to first floor units
– Common areas finishing in progress
January 2023 Update
– Driveway and parking area completed
– Exterior fencing and landscaping completed
– Apartments final touches completed
– Playground and entertainment are completed
– Common areas and stairways nearing completion
February/March 2023 Update
- Fully completed and individually titled.